
John King argued “Date of Substantial Completion” before Appellate Division
In Trinity Church v. Atkin Olshin Lawson-Bell, John King successfully argued that a contract clause defining the “date of substantial completion” was enforceable resulting in dismissal of plaintiff’s case.
John H. King argued the cause for Defendant/Respondent Atkin Olshin Lawson-Bell, an architectural firm, in a case where plaintiff Trinity Church appealed from four trial court orders dismissing on summary judgment its complaint against an architect and several other defendants based on alleged construction defects. The Appellate Division Court concluded that plaintiff’s complaint was properly dismissed because it was filed beyond the statute of limitations which, by contract, commenced on the date of substantial completion of the construction project. While the court agreed with plaintiff that the standard contract clauses abrogating the discovery rule are subject to equitable tolling, the court found that plaintiff did not establish a factual basis for equitable relief. Accordingly, the court affirmed the trial court’s dismissal of plaintiff’s case.
“plaintiff’s complaint was properly dismissed because it was filed beyond the statute of limitations which, by contract, commenced on the date of substantial completion of the construction project.”
The Facts
In 1994, Trinity Church (Trinity) contracted with defendants Atkin Olshin Lawson-Bell (AOL-B or architect) and E. Allen Reeves, Inc. (general contractor), who in turn subcontracted with defendants Bruce E. Brooks & Associates (HVAC and plumbing) and Gallo Masonry, L.L.C. (mason), and third-party defendant Maria Isabel G. Beas (mason consultant). The contracts were for renovations to Trinity’s historic church located in Princeton, New Jersey, and construction of an addition to the structure.
The relevant contracts, which were also incorporated by reference in the subcontracts, contained clauses providing that the statute of limitations for any cause of action arising under the contracts would run from the date of “Substantial Completion.” The architect’s contract provided:
“Causes of action between the parties to this Agreement pertaining to acts or failures to act shall be deemed to have accrued and the applicable statutes of limitations shall commence to run not later than either the date of Substantial Completion for acts or failures to act occurring prior to Substantial Completion, or the date of issuance of the final Certificate for Payment for acts or failures to act occurring after Substantial Completion.”
By its terms, the contract pertaining to the architect was governed by Pennsylvania law, which provided a four-year statute of limitations for construction contract lawsuits. 42 Pa. Cons. Stat. 5525(a)(8) (2006).
The parties signed a certificate establishing August 1, 1997, as the date of substantial completion of the project. Trinity first noticed problems with the construction in April 2000, particularly problems with the mortar, and began communicating with AOL-B about those issues. The parties, including Reeves and Beas, held a series of meetings at which they discussed possible causes of the problems and possible solutions. Finally, AOL-B hired a consultant, 1:1:6 Technologies, Inc., which investigated and issued a lengthy report in September 2002 detailing the problems it discovered with the construction. Trinity received a copy of the report, but it neither filed suit at that time nor undertook any investigation of its own.
Two years later, on September 13, 2004, Trinity filed a two-count complaint, alleging that a defective mortar had been used in the construction and that the HVAC and plumbing work had been done in a defective manner, causing a mold problem and water damage in the building. After filing suit, Trinity hired an engineering consulting firm to evaluate the construction; this firm issued a report on August 24, 2005, and a second report on October 13, 2005. In September and October 2005, defendants filed motions for summary judgment seeking dismissal of the complaint on statute of limitations grounds. On October 18, 2005, Trinity filed a motion for leave to amend its complaint to “clarify” the existing counts of the complaint, to add defendants, and to add a count concerning defective lamination of the church doors and a count concerning “defects in the wall structure of the Church” based on Trinity’s expert reports.
The Trial Court’s Opinion
In an oral opinion placed on the record on January 6, 2006, Judge Jacobson granted summary judgment. She concluded that, in the “Substantial Completion” clauses of the contracts, Trinity bargained away its right to invoke the discovery rule as a means of avoiding the bar of the statute of limitations. Addressing Trinity’s claims for equitable relief from the bar of the statute, she reasoned that “[t]here’s no claim in this complaint for fraud. There’s no claim even for misrepresentation.” She also noted that no such claims appeared in the proposed amended complaint which was the subject of plaintiff’s motion.
Judge Jacobson found no evidence that defendants had tried to mislead Trinity or to convince plaintiff not to file a lawsuit. She reasoned that the 2002 report from 1:1:6 Technologies revealed “significant cracking” and other problems with the construction, and this should have put plaintiff on notice to investigate and/or file a lawsuit at that time. The judge rejected Trinity’s estoppel claim: “[H]ow can I estop the defendants when they were the ones providing most of the information to the plaintiff regarding problems at the church within the New Jersey statute of limitations[?]” She found that “the church had information that there were problems with the work . . . well within the statute of limitations and for whatever reason, which is not clear on the record, they did not file the lawsuit until after the statute of limitations had lapsed.” She concluded that no further discovery was warranted and that summary judgment should be granted.
https://law.justia.com/cases/new-jersey/appellate-division-published/2007/a3022-05-opn.html
Thompson Becker, LLC provides a wide range of both transactional and litigation services for the construction related professionals and their businesses. We have successfully prosecuted and defended various types of construction related claims. Contact us at (856) 616-8886 to see how we can help you with your construction law needs.
The information in this blog post (“post”) is provided for general informational purposes only, and may not reflect the current law in your jurisdiction. No information contained in this post should be construed as legal advice from Thompson Becker, LLC or the individual author, nor is it intended to be a substitute for legal counsel on any subject matter. No reader of this post should act or refrain from acting on the basis of any information included in, or accessible through, this post without seeking the appropriate legal or other professional advice on the particular facts and circumstances at issue from a lawyer licensed in the recipient’s state, country or other appropriate licensing jurisdiction.